Fotocollage visit 17 December 2002

 Gate operation of Pilot area and field conditions


 

TC 12 needs maintenance of tertiary.

The connection between the Tertiary gate at the SDU side and the SDU needs urgent cutting of bush to promote easy inflow of SDU flow into the tertiary when required. Urgent request to Pak Suranto!

No beton stoplogs!

Beton stoplogs in the secondary gate are not advised as operation of these stoplogs will be impossible. Operation should concentrate on the sliding gates and the flapgates.

Still no trash racks in SPD gate Jalur 5

Especially when the flapgates will be operated, the trash racks are important.

Trash racks work here. Gate SPD Jalur 6

Flapgates are in principle operational, but only require a steel wire for operation with the winch. The gate operator promised that the steel wires will be installed before the end of the year

The SDU at TC 12 is perfect

The SPD near the house of Pak Suranto is still clean

Few weeds, bush growth and trash found here

The TAM in TC 12

The TAM ditches in TC 12 are still not deep enough for proper operation.

TC 12 on 16 March 2004

The quaternary and teriary canals are in perfect condition.

This area is Flooding Type B close to Type A. You see the second crop.

 